COMPLETE PACKAGING AND SHIPPING MANAGEMENT SYSTEM
Taking the Zimbabwe 2 MTPA Lithium Mine Project as an example, Xinhai formulated a strict construction plan and ensured construction progress through the coordination of the project team. At the peak of the project construction, Xinhai dispatched a team of up to 423 people from China to the project site and hired over 1,000 local employees, achieving local employment by integrating local expertise with Xinhai's technical capabilities. These measures ensured that the project went from testing to successful trial production within a year, fully demonstrating Xinhai's speed in the implementation and execution of large and complex projects.
-
Concrete for the independent foundation of the coarse crushing workshop completed
-
Concrete pouring for the retaining wall foundation completed
-
Rebar binding for the plant foundation completed
-
Equipment foundation for the screening workshop completed
-
Formwork and rebar for the tailings thickener foundation completed
-
30% of the earthwork excavation for the flotation and grinding workshop completed